Harmonic Mitigation & Reactive Power Project Planning
Evaluate an active harmonic filter (AHF) when harmonic current exceeds the target, and a static var generator (SVG) when reactive demand varies with load. Coordinate both when needed.

Match equipment to the measured problem
Compare the harmonic spectrum and reactive power trend across representative operating conditions.
Harmonic current exceeds the project target
Evaluate an active harmonic filter. Use the harmonic current in amperes by order and phase to estimate required filter current. If voltage distortion is also high, check its source before sizing.
Sucyc-AHF Active Harmonic Filter (IGBT)Reactive power varies with load
Evaluate a static var generator. Size from the measured kvar range and how quickly it changes. Check whether the site needs inductive and capacitive compensation across its load cycle.
Static Var Generator (SVG)Harmonic and reactive targets both apply
Coordinate the AHF and SVG capacities, sensing points and control targets with any existing capacitor banks. If one unit performs both functions, confirm the available current and priority settings when both demands peak.
Read the APF vs SVG guideWhat to check on site
- Measurement baseline
- Record three-phase voltage and current, harmonic spectrum, kvar and power factor at the intended connection point across typical and peak loads. Identify the agreed compliance point separately when required.
- Installation constraints
- Use the single-line diagram to confirm supply voltage, three- or four-wire topology, existing compensation and proposed current transformer (CT) locations. Check CT ratio and polarity, protection, cabinet space and ventilation against the selected equipment documentation.
Verify performance under comparable loads
Before commissioning, agree on the measurement point, operating conditions and acceptance metrics. Compare before-and-after readings at that same point with comparable loads and network configuration, using the same instrument settings.
Record harmonic current and voltage distortion, residual kvar and the agreed power factor metric. Where IEEE 519 applies, assess the applicable distortion limits at the point of common coupling (PCC).
Share your measurements for selection support
Include the single-line diagram, available measurements, existing equipment and the targets the project needs to meet.